In order to ensure the safety of bridge crane operators, more attention should be paid to certain matters when operating bridge cranes.
Precautions for operating bridge crane:
1. When lifting heavy objects in each shift (or when the load reaches a large weight), the heavy objects should be lowered again after being lifted 0.5 meters off the ground, the brake performance should be checked, and after confirming reliability, normal operations can be carried out.
2. Strictly implement the "Ten No Lifting" policy of Shandong bridge crane manufacturers:
① The command signal is unclear or chaotic, and the command is not suspended;
② Do not lift when exceeding the rated lifting capacity;
③ Unreasonable use of lifting equipment or failure to securely hang objects;
④ If there are people or other floating objects on the suspended object, do not lift it;
⑤ Failure to lift due to brake failure or other braking devices;
⑥ When lifting heavy objects directly for processing, do not lift them;
⑦ Slant pulling and hanging without lifting;
⑧ Explosive objects are not suspended;
⑨ Objects buried underground are not suspended;
⑩ Objects with sharp edges and corners, not suspended without padding;
3. If any abnormality is found, immediately shut down the machine, cut off the power supply, check the cause and promptly eliminate it.
Before the operation of the bridge crane, the single beam bridge crane with a cab should be checked by the driver before taking over the shift. The hook, wire rope and other components should be inspected according to the requirements of the inspection card. If any abnormal situation is found, it should be eliminated. The single beam bridge crane operated on the ground should be inspected by a dedicated person per shift according to the requirements of the inspection card. Any abnormal situations found should be eliminated.

| Previous:Common faults and solutions of crane pulleys | Next:What are the maintenance methods for bridge cranes |